Rungay’s Bridge, a concrete road bridge with a solid parapet over a drain.
Case studies
ActiveSM:ART Trial case study

Four SM:ART monitoring units at the half-joints of a 1940 reinforced concrete road bridge in the Norfolk fens, in a SM:ART Trial with Norfolk County Council.

Asset owner
Norfolk County Council
Structure
Reinforced concrete beam-and-slab road bridge of five spans, about 41 m, built 1940
Location
Middle Level Main Drain, Marshland Fen, Norfolk
Installed
October 2026
Instrumentation
Four SM:ART units, one at each half-joint outer face
Measured
Half-cell potential, concrete resistivity, temperature, relative humidity, tilt
Cadence
Hourly

The problem

Half-joints concentrate risk. The nib is a thin section carrying the deck reaction, it sits directly beneath a deck joint, and water carrying de-icing salts drains towards it. The reinforcement inside is hard to inspect and harder to assess without intrusive investigation.

At Rungay’s Bridge two half-joints in the centre span carry a suspended span. The joints are filled, so the bearing shelves inside them cannot be seen at an inspection.

Principal inspections run on a six-year cycle. Between them, the condition of the reinforcement in a half-joint changes continuously and unobserved. For an asset owner weighing repair, strengthening or replacement, that interval is where the uncertainty sits.

The SM:ART Trial at Rungay’s Bridge is set up to narrow that interval: hourly measurements taken at the half-joints themselves, as evidence for Norfolk County Council alongside its inspection and assessment work.

The asset

Rungay’s Bridge carries a minor road over the Middle Level Main Drain at Marshland Fen, Norfolk. It is a reinforced concrete bridge of five spans, about 41 m long, built in 1940, with two beams and a deck slab cast in place. Norfolk County Council owns the structure.

The centre span has two half-joints, which carry a suspended span.

Before the installation, AI read Norfolk County Council’s records for the bridge: inspections, assessments, surveys and the record drawings of 1939 and 1940. The drawings were rebuilt as a 3D record model of the bridge as drawn, down to the reinforcement.

3D record model of Rungay’s Bridge in its setting: a narrow concrete road bridge with solid parapets across a wide drain, set on a satellite view of the banks, fields and farm buildings.
Rungay’s Bridge’s record drawings have been rebuilt as a 3D record model.

The SM:ART deployment

Four SM:ART monitoring units were installed, one on the outer face of each beam at each half-joint. The work ran from 27th to 29th October 2026 and covered nearby Morton’s Bridge in the same visit. Structivate’s team worked from a floating pontoon on the drain, with a scaffold tower up to the half-joints.

The positions were chosen from the evidence in the council’s records and set out on the 3D record model before the installation. On site, a reinforcement scan fixed each hole before drilling.

Each unit is retrofitted through drilled holes and grouted in place, with its own connection to the reinforcement. The units are self-contained and battery powered, with batteries sized to the six-yearly principal inspection cycle, and they report over a wireless uplink to the cloud platform. Measurements are taken hourly.

The units measure half-cell (corrosion) potential, concrete resistivity, temperature and relative humidity. Tilt is recorded as a separate structural-behaviour signal.

SM:ART was developed at TU Dublin with Enterprise Ireland Commercialisation Fund support. Structivate runs the SM:ART Trials and produces the analysis and reporting for the asset owner.

Findings to date

Monitoring is underway at Rungay’s Bridge.

No readings, trends or conclusions are published here. This page describes the deployment, not its results. What the measurements mean for the structure is for Norfolk County Council to decide; anything published later will follow the council’s review and be stated as measured or modelled accordingly.

Engineering implications

The deployment does not replace the inspection regime. General and principal inspections continue; the monitoring fills the interval between them with hourly evidence from the details of concern.

The decision remains an engineering one. SM:ART provides measured evidence; Norfolk County Council weighs it alongside inspection findings, assessments and its own judgement.

What the Rungay’s Bridge deployment shows so far is the preparation as much as the installation. Before anyone drilled, the owner’s records had been read, the record drawings rebuilt as a 3D record model and the positions chosen from the evidence in the records. That way of working is what The SM:ART Trial offers other owners of ageing reinforced-concrete structures.

From the installation

Structivate’s own photography from the October 2026 installation at Rungay’s Bridge.

  • Rungay’s Bridge in morning fog: the edge beam and solid concrete parapet above a pier, with a SM:ART unit fixed at the half-joint.
    The edge beam and solid parapet above a pier, in morning fog.
  • The underside and outer face of Rungay’s Bridge in fog, looking along the edge beam to a SM:ART unit fixed at a half-joint above a pier.
    A unit at one of the half-joints, seen along the beam.
  • Two people in orange high-visibility clothing stand on a scaffold tower, backs to the camera, working at a half-joint under the bridge’s solid parapet.
    Working at a half-joint from the scaffold tower.
  • A scaffold tower on a floating pontoon with a blue guard rail under the bridge, a person working at the beam, and the drain disappearing into fog.
    The scaffold tower on the access pontoon, in morning fog.
  • A SM:ART unit fixed below the step of a half-joint, with three blue-cabled sensors in the concrete beside it and a fresh mortar patch.
    A unit beside the step of a half-joint, with its sensors in the concrete.
  • A black SM:ART unit with the Structivate name on its lid, fixed to the concrete of the beam, with blue cables looping to its sensors.
    A unit in position, with its sensors grouted into the concrete.
  • A black Structivate unit fixed to weathered concrete at Rungay’s Bridge, with three probes cabled into drilled holes.
    A unit with its sensors cabled into the concrete.

What happens next

Monitoring continues. Findings published here will follow Norfolk County Council’s review.

View case studies

Have a similar structure?

Applications are open for the Spring 2027 SM:ART Trial. Half-joint bridges like Rungay’s are one fit. The next cohort is expected to consider a wider range of reinforced-concrete structures.